on 07-07-2011 7:59 AM
Hello,
We have items that are planned in the ECC not in APO. The Items are mrp type "PD" in ECC since they usually open manually prod.orders for these items. They have a PDS in APO .These prod.orders are scheduled in APO using the planning board. But, sometimes planned ordres are created in the ECC in the planing run. These planned orders are aoutomatically scheduled (allocated) at the resource. We would like to avoid it. Any idea how?
Thanks you,
Hi,
These planned orders are allocated to resource based on whatever resource you have specified in planned order in ECC.
So planned orders created through MRP what ever resources are selected on whichever date same will appear in APO.
Do you want to pass ECC planned order to APO in deallocated status instead of in scheduled status.?
In such case you can try modifying configuration of planning procedure in APO .
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.