Budget Managed at Different WBS Elements

Former Member
0 Kudos

Hi

I have a scenario where there are 2 WBS elements at 2nd level-one for material procurement and the other for the real construction work involving services etc.

I have a separate budget for material and a separate budget for construction involving servies and other miscellaneous works.As such I procure against the activities under material WBSE-in this process at the time of GR the budget is used.now when i transfer/issue the material to the other WBS then the system consumes budget from that WBS while in reality I never budgeted the WBSE for materials.And then I need to increase the construction WBS element budget.

This is where my problem is.I do not wish to get the budget checked while issuing the materials to the other WBS element and also the budget for the material WBS element should not be increased when materials are issued to the other WBS element.

Any suggestions?

Thanks and Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

in spro--define tolerance limits exclude the Activity group 03 goods issue from the budget profile you are using. hereafter

budget would not be checked on wbse against the goods issues.

regards,