At present it picks the value from order only

when we do change the BOM it doesnt pick the new value based on the updated BOM

instead of that it picks the old value (value updated on the first production order creation)

In standard

test certificate value is updated from sales order or production order?

i check with sales order whether inspection lot is used in sale order

i could not find it

how can we pick the updated value to test certificate

if we update the configuration in sale order will ti update in production order leads to test certificate

i saw is there any option available to upate the configration data in sales order

but i could not find

i explain to user that material master update should not update the sale order

he asked me how can i get the correct value to test certificate

thanking you

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Untill & unless you create new order with new configuration & make same changes in "Certificate Profile" ,Updated specification will not appear in newly created certificate.

former_member222080
Participant
0 Kudos

thank you sir

where can we upate the certifcate profile

Former Member
0 Kudos

Have you created certificate profile in QC01

Maintain the below steps to create Quality Certificate:

1. Create a Certificate profile in QC01

2. Assign the Characterstics

3. Assign the Material, Inspection Origin and Inspection type

4. Assign the cerificate profile to material in QC17

5. Create the Quality Cerificate in QC20

former_member222080
Participant
0 Kudos

thank yo sir