If in the matrial master if we not activated for auto UD in this sense we wantt o fill any data in
QCC)>basic setting>plant dependetnt qm setting>inspection lot completion tab>Automatic usage desicion
Muhamed
1. Activating UD in Material master is mandatory incase you want auto UD .
The inspection lots must meet the following conditions:
All characteristics have been completed
None of the characteristics have been rejected
No defects have been recorded, or quality notifications created
The waiting time set in Customizing must have elapsed.
Inspection lots with the status skip lot can also be taken into account.
2. In customising in plant level setting you enter the delay time for skip lots ( Dynamic Modification)
3. Before the system can make an automatic usage decision for inspection lots with skip status, the delay time (in minutes) must have already expired since the lot was created.
4. You shoud activate skips allowed in the material master then .
5. Waiting time in hours is entered in customising such that auto ud is done by the system once this time has elapsed
You can trigger auto UD manually QA10 or through Job planning QA17
Deepak
You will have to activate auto UD in the inspection type or the material master for which you require auto UD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.