Dear Experts,
Is there a way we can configure APO to have SNP:PL-ORD to be created 2 months in advance after running Location heuristic?
Lets say we have a PReqRel on M 05/2012 in the Planning book after running Location Heuristic the SNP: PL-ORD will be created on M 03/2012 which is two months in advance with the exact quantity from the requirement.
Thanks in advance,
Marcus
This can be addressed by CTM through "order creation Frame" field of SNP2 tab of product master (/SAPAPO/MAT1).
Maximium earliness can be used in case of Heuristics.
Niteen Gonnade