on 07-05-2011 10:01 AM
Hello
I am copying a project from one Solution Manager to another. For the time of the migration I would like to lock down (dont allow further changes like adding/changing documents via SOLAR01) the Project in the old Solution Manager System. By doing that the old Project should still readable but not changeable and the status of the Project is not beeing changed.
Does anyone knows a easy way to do this without changing user roles?
Thanks
Nesimi
Hi,
GO to solar_project_admin t-code and there you can lock Structure. change document and admin tab under Scope button.
Thanks
Sunny