Maintain project budget at lower level wbs elements

Former Member
0 Kudos

Hi Experts

I have maintained budget at lower level elements.

But, unless i total up, i can not save budget.

Is there any standard setting, we makes automatic total up when budget is maintained at lower level WBS elements and saved.

Warm regards

ramSiva

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

Budget is always Top to Bottom....

Cost Planning You can Bottom to Top..

Former Member
0 Kudos

Hi,

Standard setting is not there. You have to go for development.

Regards,

Harsh.

Former Member
0 Kudos

Thank you Harsh

Can you give any further clue reg deveopment.

Warm regards

ramSiva

Former Member
0 Kudos

Hi,

Check the user exit SAPLKBPB. There was a similar query by a user recently and the user seems to have resolved the issue using this exit.

Regards,

Gokul