on 07-05-2011 6:13 AM
Hi Experts
I have maintained budget at lower level elements.
But, unless i total up, i can not save budget.
Is there any standard setting, we makes automatic total up when budget is maintained at lower level WBS elements and saved.
Warm regards
ramSiva
Budget is always Top to Bottom....
Cost Planning You can Bottom to Top..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Standard setting is not there. You have to go for development.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.