I have created the WBS element with business area. Then created the PR against that WBS element , converted the PR's to PO's.
Now I want to remove the business area from WBS element.
Now as Business area field become grayed out hence I canot remove the Business area from WBS element.
Hence I have cancelled the PO's then Cancelled the PR's. So now there is no actual cost & no commitment exists against the WBS element.
But still Business area field is grayed out for that WBS element.
Could you please let me know how to remove the business area in this case ???
Regards,
Pradip
Hi,
Once BA is grayed out then you can not change the same, this is sap std. behavior. Here you can lock the existing wbse which having wrong BA to avoid further actual postings.
Create new wbse with correct BA & then create pr & po.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try Tcode CNMASS
1. Give the specific WBSe which you want to remove the business area.
2. Then in selection criteria, select the business area blank and apply to the WBSe
3. Save and check it
Regards
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check cost element report in case there is any commitment left.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.