on 07-05-2011 5:29 AM
PRTu2019s are assigned to routing operations and we have to track the usage of PRT based on the production order operation duration and also include the cost of PRT usage in the standard cost of the material that is produced using the PRT.
What is the best practice for modelling this scenario?
Dear T33DDY,
The PRT usage can be traced by creating the PRT as equipment PRT and by using measuring document.
Check this link to get the PRT usage for each production order or as a cummulative one,
http://sap-pphelp.blogspot.com/2009/12/calculating-usage-for-prt.html
Also check these reports,
CF10 PRT: Use of PRT master in prod.order
CF11 PRT: Use of material in prod. order
CF12 PRT: Use of document in prod. order
CF13 PRT: Use of equipment in prod. order
CF15 PRT: Use of PRT master in network
CF16 PRT: Use of material in network
CF17 PRT: Use of document in network
CF18 PRT: Use of piece of equip. in netw.
CF20 PRT: Use of PRT master in orders
CF21 PRT: Use of material in orders
CF22 PRT: Use of document in orders
CF23 PRT: Use of pc. of equip. in orders
CF25 PRT: PRT Master Usage in PM Order
CF26 PRT: Material Usage in PM Orders
CF27 PRT: Document Usage in PM Orders
CF28 PRT: Equipment Usage in PM Order
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
Could you please specify what PRT means?
In general, you may track processing duration in RESOURCE_TIME_LOG and RESOURCE_TIME_MEMBER tables.
Regards,
Alex.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.