on 07-04-2011 1:39 PM
Hi all,
can anybody help me in the following issue....
in a budgeted/released cost project (WBS elements only):
i set up a budget profile (overall & annual years, and availability control against annual values), and assigned it to the project
i configured the availability control in order to issue a warning message when exceeding 110% from the budget against all activities (target group: ++)
Availability Control is active
However,
When i made a Goods Issue for a particular WBS element has the status "REL / BUDG / AVAC" with amount more than110% of the WBS element budget, the system permit the transaction and does NOT issue the warning message.... WHY??
Also, when i run CJI3 report, i find the amount of the Goods Issue in the actual cost of the WBS element,
NOTE: the availability control is working well against Purchase Orders, and FI direct postings FB60
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Search the forum before posting such basic queries. You will find your answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.