Dear Experts,

As we know whenever we put to (lock for any usage) a Production Version in R/3 this change is logged in table CIF_PPM_CHANGED which is then picked up by program RSPPMCHG. After running program RSPPMCHG the PPDS PPM in APO in return gets inactive and the description is changed to: Plan Invalid (Prod.Vers. Deleted in R/3).

The problem is our PPDS PPM is in inactive status and has a description: Plan Invalid (Prod.Vers. Deleted in R/3).

The change in PPM is dated 6/20/2011 in APO.

We already checked MM04 to display any changes for the material and the last change was dated 4/20/2011 for C223.

There is no change from 6/20/2011.

How come the PPDS PPM in APO gets inactive if there is no changes in the Production Version in R/3? Is there any other way to deactivate the PPM aside from running program RSPPMCHG? is there a log in APO to see the changes made in the PPM?

Hope anyone can help me.

Thanks and best regards,

Marcus

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Nandha,

There is no changes from recipe, routing and BOM.

The PPM is not activated unless we do initial CIF for the specific Products.

Thanks,

Marcus

Former Member
0 Kudos

Hi Nandha,

The Production Version is Not locked in C223.

I checked MM04 just now and the last change I see is dated 4/20/2011.

But in the PPM the change happened on 6/20/2011 and is now still Inactive.

We have a batch job running RSPPMCHG everyday.

Thanks,

Marcus

Former Member
0 Kudos

Hi,

Can you check whether in routing or Master recepie any changes has happened on the specified date.

or any BOM changes has happened.

Thanks,

nandha

Former Member
0 Kudos

Hi,

Can you check in C223 itself now what is the status.

1. Whether PV is locked.

2. when was the last check happened.

Thnaks,

nandha