Dear All,

We are using Scheduling agreements process.

In this, the transfer of requirements is activated from the sched.lines to PP (t-code MD04) . So the system works accordingly. Now we dont want to carry forward the last months schedule line's balance qty to the new month. say,

In a Sched.agreement, shedule lines

01.06.2011 order qty 500.... delivered 200 qty

01.07.2011 order qty 1000

01.08.2011 order qty 600

In June2011, 200 qty had been partially delivered. So business doesn't want to carry this balance 300 qty to production. Hence we assign schedling cat. CN on next month say on 1st of July'11 instead of CP for the June'11 sched.line.

Here the balace 300 qty is been deducted from the order qty of July'11, so in MD04 for the month of July system shows only 700 qty (1000-300=700) which is wrong.

1000 should be the production qty for the month of July'11 and June's shed.line should not reflect in Md04. . How to solve this delivered qty dedcting from the next month's requirement. Pls guide.

P.S : however the 01.08.2011 does not have nay problem. It is getting reflected in MD04 as 600qty.

Thanks,

Reg,

JJ

Edited by: Jagsap on Jul 5, 2011 11:08 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1091983
Active Contributor
0 Kudos

Thank You.

Former Member
0 Kudos

same issue we are facing. please tell me how to solve it.

-


I have created Sales Order (Number 1032) with following scenario and posted one goods issuance against first delivery with less quantity.

Sales Order Item

Item Item Desc Order Quantity

10 High Speed Diesel (HSD) 5000

Schedule Lines

Line: 10

Delivery Date: 07.07.2011

Order Quantity: 1000

Rounded Qty: 1000

Confirmed Qty:1000

Delivered Qty: 9500

Line: 20

Delivery Date: 07.07.2011

Order Quantity: 1000

Rounded Qty: 1000

Confirmed Qty:1000

Delivered Qty: 0

Line: 30

Delivery Date: 07.07.2011

Order Quantity: 2000

Rounded Qty: 2000

Confirmed Qty:2000

Delivered Qty: 0

Now when i goto VL01N and execute delivery on 08.07.2011 with reference to Sales Order system sum-up the previous quantity + 2nd schedule line quantity means (1500). But our requirement is that it should only propose the order qty of current scheduling lines date instead of previous + current date quantities..

Former Member
0 Kudos

how many factory calendars are you using?

former_member1091983
Active Contributor
0 Kudos

Hi

We are using only one factory calendor.

Our requirement is the DELIVERED QTY(filed name-VSMNG) is getting deducted from the next months schdule line qty in t-code MD04 . How to avoid this?

Thanks,

Reg,

JJ