on 07-01-2011 9:09 AM
Dear Sap Gurus,
Is there is any report or in table to check all the transportation Lead time settings setting for particular plant for all customers ? Because i need to upload several new Lead Time due to the updation in transportation
I want compare the differences in system and the new Lead time whih is going to be updated.
Thanks
Guna
Hi,
Try using std reports VT11, VT12 or VT14 and see if they help.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try joining VBAK, VBAP, LIKP and LIPS tables.
take sales order number, confirmed quantity and document date from VBAK and VBAP tables and populate accordingly Actual PGI date and planned PGI date from LIKP and LIPS table. You can also take BKPF and BSEG if required. From this you will be able to find the time required between punching the sales order for confimed quantity and delivery to the customer.
Thanks
Anil Hooda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.