Dear All,

In our scenario one finsh goods have 10 operations and out of that 8 operation is done in plant 1 another 2 operation is done plant 2.In this case how can i maintain routing for this finsh goods because we only maintain overall routing for finish goods.

Regards

Yogesh Sawant

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Yogesh,

You can use workcenter from other plants also in routing. Only thing is you need to check how you will handle financial part as other plant giving service to main plant where 8 operations are carried out.

We have done it before in one project to map intercompany tolling scenario.

Regards,

Santosh

wilian_segatto
Employee
Employee
0 Kudos

Santosh is right.

Please assign the relevant Work Centers (resources) to your operations in the routing.