Hi,

srm7.0, Extended Classic mode.

Create procurement contracts, automatic approval workflow.

approval is completed, the contract status has been waiting for approval.

Thanks

Sarah

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Verify via BBP_PD transaction of the contract status. If it is different from what you see on the web, press "refresh" button. (Not the one offered by the browser though.) If BBP_PD shows "Awaiting Approval", check the "Approval" tab of the contract on hte web and see who has the "open decision" (workitem).

Former Member
0 Kudos

Thank you,Jay Yang .

We set the contract is automatically approved,

But when the contract released three days,

The contract status is wait for the approval.

We press "refresh" button,Does not solve the problem.

Thank you

SARAH

0 Kudos

have you activated the auto approval work flow?.

regards

velu

Former Member
0 Kudos

Hi, velu333

Thank you for your answer.

We activated the auto approval work flow.

Sarah

Former Member
0 Kudos

Hey Sarah,

Can you check the status of your WF under SWi1. Does it show WF completed?

Also have you done the automatic WF customisation under SWU3?

Nikhil

Former Member
0 Kudos

Hi, Nikhil RGupta ,

We run SWi1,but the result is empty,

We Run SWU3, is running correctly.

Thank you

Sarah

Former Member
0 Kudos

Sarah,

You must be able to see a WF log under SWi1. Pl change the start time and check. If not, then how can we know whether your workflow is even triggered?

Nikhil