Dear Experts,
I would like to have your opinion on best practices for confirmation creation in classic scenario. Whether most organizations prefer to create confirmation in SRM or ECC? One advantage of confirmation creation in SRM is that you can avail different workflow scenario, while ECC MM does not support any workflow or release strategy for confirmation/goods receipt.
Your input on it will be highly appreciated.
Regards,
Ranjan
Hi Ranjan,
As far as best practice for confirmation creation goes , it should be decided by who is the goods recipient , what access the goods recipient have and and what type of material it is , direct or indirect ..
Ideally for most of Indirect procurement where requestor is creating a cart for himself or his department and would be reciving the good/ service himself , he/she should do the confirmation in SRM.
In case of direct material definitely GR need to be done in the ECC.
Thanks
Iftekhar Alam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.