on 06-29-2011 3:34 PM
Dear All,
While creating PR from CJ20N system picks valuation as M ie Valuated stock with reference to Project.
From where system picks this M? Is system picks from Requirement Class/type ?
Pls let me know the config node.
Thanks in advance
Hello,
You decide if you're using valuated, non-valuated or project stock in the project profile - transaction OPSA
Kind regards, Aleksandra