Hi ,

any idea if labour can be mapped in SNP as resource? how can it be done?

Regards,

Illford

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Illford,

Define labour/person as a capacity category and define a workcenter/resource in R/3.

then use this in the Routing and assign products and create a Production version for it in R/3.

when you CIF this data to APO, you will have PDS/PPM for the same.

Now, when you have planning data for this product in SNP Planning area and planning book, you can make selection on this resource or labour in the Planning table.

Let me know your set up. hope it is clears.

Thanks,

Regards,

Sandeep Kumar.S