GR not posted the R3

Former Member
0 Kudos

Hi,

I have craeted confirmation for a PO successfully. But that GR is not appearing in backend (R3) system. Could any body inform me any function module or Programme to replicate this from SRM to R3. This confirmation is showing in SRM "Follow-on Documens".

I am useing SRM 4.0 and Classic scenario.

Thanks,

Pijush

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Have you defined IDOC MBGMCR under partner profiles in SRM and ECC systems? This will transfer your SRM confirmation to ECC.

Regards,

Nikhil