on 06-27-2011 3:51 PM
We have few sales orders with future delivery dates in production system. We are implementing customer collaboration with SNC5.1.
There are few OPEN SALE orders in R/3. We want to plan for cutover so how we should plan this.
Details approach will be appreciated.
Regards,
Vaibhav
you can recreate the orders in SNC, once you have your production system setup with all masterdata and customizing, and PI is up and running, you can send all orders to SNC, and they will be re-created by the Replenishment order confirmation XML interface.