PR Delivery date as project finished date

Former Member
0 Kudos

HI,

When user is generating Service PR from project system, its delivery date is taken as a Finished date of the project. Further SAP is not allowing to edit this date.

Can anyone let me know why it is happening. My user do not want delivery date as finished date of the project, he would like to put his own delivery date.

Kindly suggest

regards

Sanjay Karnekar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I think that the date comes from the scheduling of the network activity. Go to the project builder and then display the material. On the Purchasing Data tab change the settings from 'Align the finish date' to the 'Manual requirements date'.

If you'd like to change this setting globally, you need to maintain the customizing under

Dates -> Scheduling of networks -> Specify scheduling parameters

Cheers, Aleksandra

Former Member
0 Kudos

Hi,

Thanks for your reply

Kindly note We are creating PR for external services & not for material. we are not able to see purchasing data for service PR.

pls. suggest

regards

Sanjay

former_member203098
Active Contributor
0 Kudos

ask user to maintain pl.deliv time in external/service activity.so that system consider the delivery date based on mentioned

days in pl.delivery time.

regards,