SAP CCR error /SAPAPO/CIF561

Former Member
0 Kudos

Hi,

We are getting the following error in CCR report. Have not found anything on OSS. Secondly after scheduling the dates are not getting updated from APO to ECC. Any help on this is appreciated.

Operation 0050 for order 000XXXXXXXX: Differences in 'scheduled' status

Message no. /SAPAPO/CIF561

Diagnosis

Operation 0050 for order 0000XXXXXXX has the following differences for the Scheduled (EIGP) status in SAP APO and SAP R/3:

Status in SAP R/3: Deallocated

Status in SAP APO: Scheduled

Thanks,

Sandeep

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sandeep,

You need to check /SAPAPO/CP1 (Maintaining Distribution Definitions).

You need to maintain entry for In-house production as you mentioned your production orders are not getting transferred to ECC.

If you want to read about distribution definition you can go to SPRO> APO>Integration with SAP Components> Integration via APO Core Interface (CIF)> Basic Settings for Data Transfer> Publication> Maintain Distribution Definition

Once you maintain this and you have CIF model active for production order then data will flow automatically to ECC and you should be able to solve your problem.

I hope this helps.

Thanks,

Anupam

Edited by: Anupam Sengar on Aug 11, 2011 12:24 AM

Former Member
0 Kudos

Hi,

Can you check in /SAPAPO/CP3 what is the setting defined for publication type " inhouse production" under Retransfer.

Her you can specify whether changes to planned orders or production orders in SAP R/3 that lead to rescheduling in SAP APO are automatically retransferred to SAP R/3.

Thanks,

nandha

wilian_segatto
Employee
Employee
0 Kudos

Hi Sandeep!

What happens if you try to reconcile these faulty orders? Are they correctly sent to APO or R/3 and the systems are in sync?

In this case the Publication Settings as already stated do have participation on this behavior.

Will