on 06-26-2011 12:08 AM
I am using drill down report - CJE0 - CJE6. I need to add additional data to the reports such as the due date. I have added the Project Def. to the reports and can put some additional data on the report. Is there a way to provide additional data for the WBS elements as well.
there are a lot of threads available about report painter..
please search the forum...