Hello experts,

Can any body guide me to create the Process schema for N-level approval in RFx.

My requirement is based on RFx target value, Document type N some custom fields like (Mode of Tendering).

For this purpose, we are going to maintain one custom table with the above said fields like If the value falls under $1000 with the Tender mode as '101' N the Document type as 'BID' then need to go for 2 level approval like that.........

Appreciate your quick reply.

Regards,

Krishna Prasad M.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

You can just add the process levels one by one and change the agent (approver)

I realized this as the following:

For BUS2200

Process Schema: 9EV_RFQ_00S (Returns the constant : 9C_BUS2200_EX01)

In 9C_BUS2200_EX01

There is only two levels in the standard, one is the manager approval , the other is the auto-approval.

I added one after the first one , and change the "Resp. Resolver Name" to "RR_MANAGER_OF_MANAGER".

Wish it helpful.

Regards,