Contract price overwrites manually entered price in SC

Former Member
0 Kudos

Hi,

We have contracts for some product categories. They are there to default a supplier. But the price in these are 1 EUR. The user then changes the price in his/her free-text SC. But when the PO is created in ECC automatically, the PO has the contracted price instead. Is this std behavior?

We are in SRM 7 classic scenario.

BR

Anders

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member183819
Active Contributor
0 Kudos

hi

free text contract item does not have UOM . SO po creates only with sc uom only.

Muthuraman

Former Member
0 Kudos

Hi

Please check in ECC for following customizing

SPRO>MM>PURCHASING>ENVIRONMENT DATA>DEFAULT VALUES FOR BUYERS

Also check the entries in SU01(Creator of PO) under Parameters Tab for EVO Settings

Thanks

Trinath

Former Member
0 Kudos

Hi,

If you have assigned the contract as source of supply then when PO is created the price is taken from the contract.

This is standard feature.

I am not sure what exact steps you have done to comment if its standard behaviour.

Regards

Sam

Former Member
0 Kudos

Hi Sam,

The steps we have done is the following

1. Contract with material group only (no material nr) is created with dummy price 1

2. Free text SC is created with this material group and gets price 1

3. Price is changed before submit to 10

4. PO in ECC still has price 1.

BR

Anders

former_member183819
Active Contributor
0 Kudos

ok.

1. sc created with price 1.0 and refered product category contract

2. before approval did u change the price as 10 in the sc

3. now PO creates and shows 1 only ?