cancel
Showing results for 
Search instead for 
Did you mean: 

OpenPS4msp Version: 4.03.01

Former Member
0 Kudos

Dear All,

I am Using OpenPS4msp Version: 4.03.01.

I have a Project Definition where we have Multiple WBS (upto level 2) and we are using single network.

Activities are distributed in various WBS levels (Lowest WBS).

I am unable to download Actual Duration.

The Actual Start date is downloaded.

Also I think for Activities with 100% completion, the Actual Finish date also needs to be Downloaded.

In Settings/Object Type/ I have selected Download Actuals.

Regards,

MAK

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi MAK,

The actual work and duration are downloaded when you download resources.

It is mentioned in the point 53 of the note 579761

"When downloading projects with actual data, the actual work that has

been completed by an activity element on an activity in R/3 is

assigned to the resource of a task in MSP."

Please note, when there is a work center / plant associated with an activity the

actual work and durations are downloaded otherwise actual work and duration

is not downloaded. Please check the downloads for activity with work centers.

I hope this helps.

Thanks a lot and kind regards,

Enrique Sosa