Hello Experts,
Can anyone guide me about how we calculate Set Up time from PPDS PPM and using resource? Please reply only if you can guide field by field explanation.
Thanks.
Best Regards,
Chandan Dubey
Below is the calculation: -
Capacity consumed = [(Production Order * Variable Cons Qty) / Base Qty] + Fixed Duration of Set up