Hello Experts,
For some reason the shipping processing time is not considered for delivery scheduling . I believe this is the time for preparing the shipment and we want to add 24 hrs in material master data to be able to calculate during delivery scheduling.
Please advise
Thanks in advance
HI,
For delivery scheduling enter time
IMG >> SD >> Basic functions >> delivery scheduling and transportation >> maintain duration
Maintain here route, pick/pack & loading time
For in house production maintain time in material master in MRP view
Then now system will take in account what is production time + pick/pack + load time and then will schedule
Kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kapil,
Thanks for your response.Our Requirement is to add 1 day time in material master for calculating the PGI date/material available date in the Sales order. We want to control the shipment preparation time based on material master time.For example
When the sales order is created , the material available date is 6/24 , PGI date is 6/24. For a specific material we want to add 1 day time period for processing. Then I will see either the PGI date to be 6/25 or the Material available is 6/25 , what ever is possible.
Is this possible with a user exit ?
Thanks in advance
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.