Dear Experts,
One of my clinet is requesting for Patch Upgrade before Go-Live and we have complted realization phase.
Scope is ECC 6.0, SRM 7.0, EP, BI, PI, MDM.....
Is it recommended to do the patch upgrade before Go-Live or do we need to do it after Go-live.
If we do patch upgrade now (after realization phase and before Go-Live), what are the implications of such a patch upgrade.
Pl help with answer.
Thanks
Madhu K
Well it makes no sense to Go-Live just to run patches in a month. You should take advantage that you have a team in place and import the patches now.
As mentioned before testing is the key...
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
If you are planning for patch upgrade then make sure that you should have enough testing time to test all the scenarios to avoid last time surprises.
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.