Requirememnt not show from MRP

former_member214153
Active Participant
0 Kudos

hi,

SAP PP GURU,

We are using discrete manufacturing with MTO scenario and using the MRP run from MD50 and for Raw material we use MD01 with user exit EX1 & user exit parameter D01,PK1 for a specific material material.

Now problem is the requirement of material not show please tell me where i saw the requirement (what the t-code for seeing the requirement in PP)

Thanks,

Anurudh singh rathore

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Anurudh

Use the T code : MD04, enter the Material & Plant, ( This is the Stock requirements List)

Here in this, you can find all the receipts & requirements of the materail dynamically.

Hope this will help

Regards, BRS.REDDY

former_member214153
Active Participant
0 Kudos

thnaks for your replay but i want order vis and its quantity not show correct

Answers (0)