Requirment ;

To have stock report which have the normal as well as project stock.

like we have MC.9.

But the problem in MC.9 is that, project stock does not appear in this.

Thanks,

Vikas

Accepted Solutions (1)

Accepted Solutions (1)

sanilbhandari
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

Try report J_3RMOBVED . Click Special Stock for Project Stock Display also

Regards

Sanil Bhandari

Former Member
0 Kudos

Not able to open this J_3RMOBVED ...

can you suggest any T-Code.

Thanks,

0 Kudos

Hi Vikas,

Go to transaction SE38, enter the report "J_3RMOBVED" & press "Execute".

There you can select the stock type u wanted.

Hope this will help you.

Regards,

Ritesh

Answers (3)

Answers (3)

kailas_ugale
Active Contributor
0 Kudos

Hi,

t-code MB52 will give project stock to for plant and storage location ,try this

Regards

Kailas ugale

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Use Report MB52, in selection screen, select "Also Select Special Stocks" with Special Stock Indicator "Q" i.e. Project Stock.

And specially for Project Stock, you can use report "MBBS".

Former Member
0 Kudos

Thanks,

But in "MBBS" only project stock appear.

I want to have the t-code like MC.9, in which we can do analysis.

Thanks,

Vikas Rander

former_member533946
Active Contributor
0 Kudos

Hi dear,

You can create your own Z report by copying MB52. In MB52 you get the special stock indicator(e.g.'E' indicates Sales Order stock, 'Q' stands for Project stock). Ask ur ABAP er to make use of this special indicator and bring the Project code or WBS in that report so that ur requirement is met.

Former Member
0 Kudos

Thanks for your answer but that opetion is known./

I wonder, do sap have standard material analysis report like MC.9 uin which project stock also appear.