Hi ,

My scenario is

We will create purchase order with two line items( 10 & 20) with quantities 10 nos and 10000 nos. First line item(10 nos) is a sample and free of charge. We will generate the inspection lot for the first line item during GR for Purchase order. If the inspection lot is accepted for the sample, the second line item (Qty 10000 nos) direcly goes to un restricted use during GR. If not, the second line item will create the inspection lot.

The above scenario can be acheived, if the purchase order has single line item with Quantity 10010 nos through DMR.

Can you help in this regard.




select second line in dme and click on stage button above.

here u can find that no. of skip it should be 1 , max duration keep blank, next stage: 1 (this will shift the 3rd lot to inspection)

just check these settings.