Strategy 40

Dear Experts,

Currently utilising SCM7.0. Successfully have working the concept of 'planning product' or strategy 40 in APO. The result of this is the forecast consumption completes accurately as seen in /SAPAPO/RRP3.

However when investigating the same data within the SNP planning book, the consumption of the forecast is at best inconsistent; can anyone provide any insight as to whether there is a specific amendment need for example to a macro and in particular the DEMAND_CALC function?

any working examples would be useful.

Thanks in advance

Paul

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question