cancel
Showing results for 
Search instead for 
Did you mean: 

How to change material quantity in plant

Former Member
0 Kudos

Hi,

am using BAPI_MATERIAL_AVAILABILITY for availability check but material qty its showing zero. So how i can change that ?

Thanks,

arun

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

For changing material quantity for any material in particular plant ,you have to add or remove the stock through MIGO (Good receipt or Goods Issue ) Transaction.

Answers (2)

Answers (2)

former_member533946
Active Contributor
0 Kudos

Hi dear,

If the stock is not there u can add the stock by one of the following methods

1) Create PR,PO,GR

2) Use MB1A - 202 , MB11 - 202 to upload the stock.

3) Use initial upload

4) MI10

Once u have the stock then u can run BAPI.

former_member182673
Active Contributor
0 Kudos

Since there is no stock available the BAPI is showing zero quantity on ATP check. Create stock on specific material and then run this BAPI to check..