CIF planned order transfer ECC6.05 to SCM 7.01

Hi colleagues,

I have the following problem with ECC 6.05 and SCM 7.01 integration.

Production order transfer (change, creation) via CIF is ok.

But for planned orders it works only one way from APO to ECC.

When I create or change a planned order in ECC it doesnt get transferref to SCM. Nothing in SMQ1 or SMQ2.

Has anyone seen any note on this?