Hi,

In Network we have added a component without SAP material number, direct purchase requisition is created.

For this network,requirement date is 15.06.2011 and we have added the component and created the PR on 13.06.2011.

When we check the PR its delivery date : 13.06.2011 and release date is :15.06.2011.

So as in the network component requirement date is converted into the release date of PR?

But same scenario as above when we put planned delivery time in component

without SAP material number as 5 days and save it, PR is created.

In this PR : Delivery date is : 18.06.2011 ( 5 Day + Creation date 13.06.2011)

and : Release date is : 13.06.2011 ( date on PR created through Network)

What is the logic of release date in PR created throguh network with out sap material number?

Why it is taking as requirement date as release date in PR when there is no plan delivery

time of GR processing time maintain?

There is no procumbent lead time maintain in configuration at plant level.

Please help in this regards