Batch job allocation of stock:

Former Member
0 Kudos

Dear SAP Gurus

Batch job allocation of stock:

For eg : Japan order: 1104104099 with requested date on 12th April has not been allocated to the stock, whereas several India order such as: 1404209680 with requested date later such as 9th May has been allocated the stock.

The batch job allocation of stock should be based on first in first out in order to be fair.

Why system is not giving priority in allocation of stock to Japan order which is earlier than the India order

Please clarify?

Thanks

Guna

Accepted Solutions (1)

Accepted Solutions (1)

madlercm
Active Contributor
0 Kudos

Have you tried running V_V2?

Answers (0)