Sucontracting MM-SUS

Former Member
0 Kudos

Hi,

Im working in MM-SUS scenario.

I go to create Purchase requisition of sucontracting in ECC system, this purchase requisition are sent to SUS (supplier self service)? How? SUS allows show positions subcontracting of purchase?.

The vendor can see these purchase requisition in SUS system?

Thanks for your help!!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Mariposa,

PO's are transfered from R/3 to SUS not PR.

Please convert PR to PO and check if the necessary setting are done in MM to sent the PO to PI which will send the PO to SUS.