PIR and material master price

Dear all,

Say i have standard price maintained in material master as $2.00 per piece. This price is inclusive of freight cost or duty cost. Where as in PIR it is $1.20 only on material cost. the 80cents of freight and duty i built in PO condition by percentage.

1) May I know if it is ok to have PIR and standard price at different price because 1 want to calculate the freight and duty condition in PO by percentage?

2) when there is difference in amount during migo or miro against $2.00, then will go to price difference.