on 06-15-2011 7:20 AM
Hi Collogues,
We have simple production type. Production order with production versions.
16 production lines (work centers) with different rates. 1 operation per routing.
I want to use in capacity leveling CM21 to dispatch planned/production orders on these 16 lines.
The problem is that when I dispatch a pln/prd order in CM21 on a work center nether routing nor production version gets updated.
Your suggestion are welcome.
Solution found.
Set for each production version "Production line".
Then go Mf50 switch to graphical planning table. It updates routing when I move planned order over work centers.