Update ST/PI Plugin - Init delta queue

Hi guys,

Yesterday, our basis team, asked me to clean all extraction queue in BW. They will update a plugin (ST/PI) that control the connection between the enviroment BWP and ECP.

I have to delete all the queues in transactions SMQ1, RSA7 and empty the setup table using LBWG. The note 1081287 will give a better explanation about this.

My question is:

Will I have to restart all the LIS extraction again with full update?

For example, to start the datasource 2LIS_08TRTLP, I have to execute the transaction VTBW and after execute an init delta in BW with all data.

Is there a way to start this delta without carry all the data again?

I wanna carry only the new data to BW to update the cubes

thanks

Paulo