Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Should we use only one process order for each CO-product?

Dear All,

We have process orders. One process order opens per day.

Now we need to use CO-products and calculate actual cost of goods manufactured for them.

Suppose we have 30 process orders. We have specified Apportionment Structure in Material Master.

Then when we create process order we define actual Apportionment Structure in setllement rule as well.

After we have setlled all process orders would Material Ledger/ Actual costing run consider this Apportionment Structures from all 30 process orders?

I heard opinion from Consultant from SAP that it will not work.

Has anyone heard anything?

Best regards,

Kamila.

Former Member
Not what you were looking for? View more on this topic or Ask a question