Hi Gurus,

I am working on the Repeditive MFg Process. Actually our process is converting 25kg bult material into 7g sachet. so we are keeping this 25kg bulk materil as a raw material in 7g FG Bom and doing MD11, MF60 , and then MFBF using Assembly Backflush -post with correction.

ISSUE is:

System not considering consumed quantity entered in production confirmation. It is rounding up.

For Exp: While doing production confirmation, even though consumed quantity entered as 73 kg, but system rounding up to 75 kg (nearest multiples of 25 kg).

Note : (Alternate Uom conversion is 1 Bag =25Kg in material master)

How to get the exact consumed qty (UOM Kg) conversion to BAG .Like Consumed is 73 KG and the Bag conversion should be 73/25KG =2.92 Bag instead of rounding 73/25=3 Bag what we are getting now.

Thanks,

Manikandan.P

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Manikandan,

If my understanding is correct, then there is no meaning in maintaining the stocks of unit of measurement like bag,barrel,drums

in decimal places.For eg a stock can be as 3 bag or 10 drum etc.

Allowing decimal places through CUNI for these UOM is not recommanded.

Check and revert back.(Also I guess there are similar issues that have been posted earlier,search and find the suggestions in

those threads).

Regards

Mangalraj.S