Dear SAP experts

for now, In third-party process, condtion base value of billing only come from oder doc's.

but we want to change condition base value of billing from PO doc's for some condition type.

(actually, we want PO Quantity as a condition base value in billing process)

where can i apply alternative solution?

Regards.

Juyoung

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member303858
Contributor
0 Kudos

HI,

To elaborate, you can change the condition base value settings in the pricing procedure for the condition type.

Take help of ABAPer and let him know what exact qty or value you want system to pick up while processing billing docs.

Prior to do any changes, please also ceck if the new changes are impacting any old logics...

Hope it helps..

Regards,

SB.

gomatheeswaran_palaniappa
Active Contributor
0 Kudos

Dear Juyoung,

You can customize condition base value in pricing procedure against the condition type.

Regards,

P Gomatheeswaran

Former Member
0 Kudos

Hi,

You can't change the Condition Base Value while creation of Invoice but can change the Condition value through Customizing.

Best Regards,