Hello Gurus,
I have a problem with a BI DataSource activation on ECC side.
I found that a requirement to do this implementation is "swith on" the OPS_PS_CI_1 (Project System Enhancements in functionality & Usability) Business Function on SFW5 t-code (Swith Framework Customizing).
I know it is an irreversible activity, so I ask you: there are some issues or preliminary steps linked with this activity?
In ECC-PS side or others modules?
I must activate these datasources, then I have to swith on this business function.
Thanks in advance,
Vito Savalli.
No other things required
Just select and activate and all the functionality will be available
Do in DEV to make sure your current system is not affected
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can acitvate this, once you activate this additional nodes will be activated in SPRO, example under easy cost planning few more nodes will be enabled. based on your business needs you can configure the additional nodes. It will not distrub the current functionality in the system.
thanks
Regards
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.