Did you mean: 

"Description for reference" in Shipment Cost

Former Member
0 Kudos

Can we change the "Description for reference" in Shipment Cost VI01?? Current standard brings in the shipment number. Is there any way which we can bring in the DO number instead?

In this case, we have a reference of one DO, one Shipment number.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can change in this exit V54C0001 and change the include ZXV54U09 to change the description.

Former Member
0 Kudos

Thank you, solved problem with exit V54C0001. Now this appears automatically in VI01 and gets transfered to FBL3N line item.

Cheers

Answers (1)

Answers (1)

david_ruiz
Active Participant
0 Kudos

Hi Philipx,

You could try with following enhancements

- BADI_SCD_SAVE

- EXIT_SAPLV54U_005

- EXIT_SAPLV54U_004

good luck,