In OPU3 i maintained automatic scheduling.

If we have 8 operations in one production order.

after first operation is confirmed with actual deviation date ie as per routing its 50 min actually its taken 70 min.

so remaining operation s to be reheduled automatically after preceeding operations are confirmed.

Presently when we are going to Co02 then after clicking schedule order only its rescheduling..

we want this automatically Is it possible.

Regads,

srihari.M

Former Member
Former Member replied

Hi,

OPU3 automatic scheduling check box tick will only work in case of when order is created i.e. manually by CO01 or by converting from planned order to Production order which is already happening in your case.

It doesnt reschedule anyways other operations based on delayed timings of previous operations.

If you dont maintain tick in automatic scheduling check box in production order creation there will be status updated as NTUP - Dates not updated when you create & save order. So this check box just provides you automation of scheduling at the time of order creation.

Hope this clarifies your doubt.