Former Member
0 Kudos

whils doing sub contract PO

the following error

"" MRP parameters for plant 'JJPL'(plant) have not been maintained""

1. i have not maintain any MRP in RM or FS

2. while doing sub contact PO .. MRP parameters we must mainatain ?? with out MRP we can not create sub contact ??

alifff

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187989
Active Contributor
0 Kudos

Check procurement type,special procurement is configured for plant ?