Hi Experts,

I have created PO with amount 4.4 crore & Posted MIRO of amount 3.3 crore but in CJI5 report still showing 4.4 crore.There is down payment of Rs.48000.What could be the reason for showing 4.4 crore in CJI5.

Thanks & Regards

Nitin A

Edited by: Virendra Pal on Jun 13, 2011 1:26 PM

Failed to search - to be deleted on weekend

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Try running the program listed below and then run CJEN and check.

RKACOR10

RKACOR04

RKACOR04

Former Member
0 Kudos

Hi Gokul,

Thanks for your reply

After running RKACOR04 program it is giving message No error record was found for the selection criterion from the calculation of actual costs for the work confirmed.

Regards

Nitin A

Former Member
0 Kudos

Try running RKANBU01 and then CJEN. Revert with your findings. Also refer this note,

Note 152571 - Composite SAP note: Missing or incorrect commitments