Hi people,

Could you tell me if there are some impacts if I do the follow?

"I have to change the configuration in OKTZ"

Some accounts will pass from one "cost component" to another one.

I know that after that when I will calculate the standar Price, the system will consider the new Cost Element, but I would like to know if there is some impact. If I have to take atention in some thing or execute some transaction after that.

Do we have to do that ate the of the month, before some posting in next month?

And the historical information in the CKM3 - material 3S? How it is showed in past manths and the current month?

Thanks for your help,

Rosana.

Former Member
replied

Hi Rosana,

Regarding to this case, please refer note 434873 which describes the recommended procedure and the problems to be expected when changing the cost component structure in detail.

regards

Waman